Power protection system for Infrax CVBA integrated utilities, a new case study

In 2016, Infrax, the Belgium operator of electricity and gas distribution and sewage networks, asked CE+T Power to assure very high power availability for its mission-critical utilities management system.

To meet this need, we provided Infrax with AGIL UPSs.

Patrick De BraekelerIn this new case study, Patrick De Braekeler, CE+T Power Sales Manager for Belgium, explains the detailed solution, including a dual redundant AGIL UPS installation, with 3-phase input, single-phase output capability and up to 80 kVA capacity for each UPS.

Infrax benefited from a successful installation, performed without interruption to Network Operation Center (NOC) operations. The NOC now enjoys very high power availability from an easily scalable UPS system and A-B power distribution network with competitive OPEX costs.

 

cet-power-case-study-infrax